Client : Ministry of Water & Environment, Local Water and Sanitation Corporation

Location : Aden Governorate

Awarded Date : November, 2008

Completion Date : February, 2011


The scope of works comprises the review of design, site clearance, site survey, supply of all material and equipment, construction, installation, interface works for completion of existing structures, as well as engineering construction, supply and installation of new pumping stations and sewerage schemes, lateral sewers including house connection, testing and commissioning, final completion, and maintenance of the entire sewerage project.

Installation of lateral sewer pipeline approximately 9km, 125 new gravity manholes and 70 inspection chambers.